Price a brand strategy project by the number of people who can say no
Deliverable count predicts your production cost and nothing else. Four pricing models, the arithmetic behind them, and the line to put on the quote.
On this page · 7 sections
- 1. Deliverable count predicts your production cost and nothing else
- 2. Agreement cost curves because disagreements come in pairs
- 3. Four ways to price a brand strategy project, and the behavior each one buys
- 4. The same project at two approvers and at seven
- 5. Put the alignment cost on the quote where the client can see it
- 6. When a day rate is honest and a fixed fee is a lie
- 7. The question that has to be answered before you write a number
Two studios quote the same brand strategy project. Same four deliverables, same eight weeks, same two people doing the work, and the two prices land within a few hundred dollars of each other. One of them makes money and the other gives away six weeks, and the difference was settled before either of them wrote a number down: the first client had two people who could kill the work, and the second had six.
Deliverables tell you what you’ll produce. They don’t tell you what you’ll spend.
Deliverable count predicts your production cost and nothing else
Every quote template asks the same question, which is what you’re going to hand over. Four workshops, an audience map, a positioning document, a messaging framework, a 12-month activation plan. Add them up, apply whatever a day costs you, add margin.
That’s a sound method where production is the cost. On a photo shoot or a website build it mostly is: the hours go into making the thing, and the client’s job is to approve it at the end.
Strategy work carries a second cost center, and on a difficult engagement it’s the bigger one. The document is the easy half. The other half is getting a group of people to commit to a decision each of them will be measured on, several of whom would prefer a different decision, at least one of whom never wanted to buy strategy in the first place. That happens in sessions, redrafts and corridor conversations, and none of it appears on the deliverable list.
The list still earns its keep, doing a job the quote template never asks it to do. Put a verdict of sell, bundle, or refuse against each of the usual line items and you find out which half of your scope is production dressed up as thinking, which is worth knowing before you price either half.
Agreement cost curves because disagreements come in pairs
Each person who can say no costs you three things.
An input session, because an approver who wasn’t consulted will use the veto to make that point. A review pass, because they’ll read the draft and have responses you have to process. And, the expensive one, a reconciliation with every other approver they disagree with.
The first two are linear. Five approvers, five interviews, five sets of comments: irritating, forecastable, easy enough to quote for. The third is pairwise. If the finance director wants the positioning to support a price rise and the sales director wants it to make discounting easier, that’s one live disagreement, and settling it costs a session, a rewrite, and a fresh review from both of them. Three approvers give you three possible pairs. Five give you 10. Seven give you 21. Most pairs never argue, but the number that can grows as the square of the headcount, and you only need a third of them to fire to lose the margin on the job.
The veto count is the input that predicts the fee, and it only works if you’re strict about who counts. An approver is someone who can stop the work, not someone who has to be kept informed. Those are different lists and the second one is always longer. Working out which names belong on the first list is a piece of work in its own right, and it belongs before the quote, not after.
Four ways to price a brand strategy project, and the behavior each one buys
Day rate. You bill time. The client’s cheapest move is to buy fewer days, and the days that look most cuttable are the alignment sessions, because they don’t produce anything anyone can hold. Your pricing model is now rationing the exact activity that reduces the risk. You’ll be asked whether the finance director’s interview is really necessary, and the honest answer, that he can kill this in November, becomes an argument you’re having on your own time.
Single fixed fee. One number for the whole thing. The client’s cheapest move is to get more inside it: another workshop, one more round, a version for the board. And you’ve absorbed all of the veto risk at a price set before you knew the veto count. Against a client you’ve worked with three times that’s a reasonable bet. Against a new one it’s a coin toss quoted as a certainty.
Phased fixed fee. A priced diagnostic first, the main phase quoted once you’ve been inside. The client’s cheapest move is to get through phase one quickly, which is harmless, because phase one’s job is to surface the approval structure and it does that whether or not anybody lingers. For a client you don’t know, this is the default, and it’s the same argument as getting paid for the thinking you’d otherwise hand over in a proposal.
Retainer. The unit is cadence: so many decisions a quarter, at a monthly number. The client’s cheapest move is to bring you more decisions, which is the only incentive on this list you actively want. It goes wrong where there aren’t recurring decisions to bring, and a one-off repositioning on a monthly fee is the shape that dies at the first budget review — a fixed-fee project with worse cash flow and no ending.
Those four aren’t equally good and the choice between them isn’t a matter of house preference. One question separates them. Do you know the veto count before you have to give a number? If you do, quote a fixed fee and name the approvers in it. If you don’t, don’t quote the main phase at all: sell the phase that finds out. A day rate is what’s left when neither of those is available — a fallback, not a policy.
The same project at two approvers and at seven
Made-up company, made-up rate, real shape.
One brand strategy project, four deliverables, sold into a company of eight people. You estimate 14 days of production: interviews, synthesis, writing, the presentation. Use $1,000 a day, a round number chosen to make the sums legible. It isn’t a rate. Swap in what a day costs you and every ratio below survives.
Three more inputs, all guesses. Calibrate them against your own last five projects; mine are here to make the shape visible and nothing else.
- One day per approver, covering their input session and their pass over the draft.
- Half of the possible pairs produce a live disagreement, the kind you can only settle with a rewrite.
- Each live disagreement costs a day and a half: session, rewrite, re-review.
| Approvers | Production | Input + review | Reconciliation | Total days | Cost |
|---|---|---|---|---|---|
| 2 | 14 | 2 | 0.75 | 16.75 | $16,750 |
| 3 | 14 | 3 | 2.25 | 19.25 | $19,250 |
| 5 | 14 | 5 | 7.5 | 26.5 | $26,500 |
| 7 | 14 | 7 | 15.75 | 36.75 | $36,750 |
The scope never changes in that table. Same four deliverables, same 14 days of thinking. Going from three approvers to seven adds $17,500, which is more than the entire production side of the job.
Run it the other way for contrast. Add two deliverables to the three-approver version, a naming exploration and a tone-of-voice guide, six days of work between them. The total moves from $19,250 to $25,250: a 31% increase, visible on the brief, priced on the quote, and almost certainly charged for. The four extra approvers add 91% and appear on nothing.
The model has a case it handles badly, and it’s a common one. A founder-run business with exactly one approver scores zero reconciliation days, and some of those are the worst-margin projects you’ll ever run. What the pairwise term really counts is unresolved disagreements, and one person can hold several of those on their own. He wants to charge more, and he wants to keep the customer who’ll leave when he does, and you will argue both sides of that with the same man on three separate afternoons while he changes his mind between them. Veto count works as a proxy because disagreement usually lives between people. Where it lives inside one, price him as three.
Put the alignment cost on the quote where the client can see it
The common workaround is padding. You’ve been burned before, so the number goes up by a fifth and you don’t say why. That moves the money without moving any of the information, and the client’s reasonable conclusion is that you’re expensive.
Break it out instead.
| Line | Fee |
|---|---|
| Strategy development, 14 days | $14,000 |
| Alignment, three named approvers | $5,250 |
| Fourth approver | $3,250 |
| Fifth approver | $4,000 |
Beyond five, stop quoting and ask for a conversation, because a six-approver strategy project has a design problem that money won’t fix.
Two things happen once that line is on the page. You get paid for the work, which is the smaller one. The larger one is that clients remove people. Told that the marketing director’s dotted-line boss costs $3,250, a founder will quite often decide that he doesn’t have a veto after all. You’ve bought a cheaper project and a better one in the same conversation, because the fastest available improvement to any strategy engagement is fewer people who can stop it.
Expect the line to be challenged, and rehearse the answer. “Why am I paying extra for my own colleagues” is a fair question with a boring answer: every additional approver buys an interview, a review pass, and an argument with everyone else on the list. The third item is the one that quietly doubled the fee on the last project quoted without it. Clients accept this more readily than most studios expect. They’ve sat through the meetings.
The line earns its place again in month three, when a new hire turns up in a review with opinions and a mandate. You’re not renegotiating; you’re applying a term you both signed. A good half of what gets called scope creep is a settled decision being reopened by somebody who wasn’t there when it was made, and one question tells you whether to absorb that or invoice for it. A named approver list is the cheapest defense against it there is.
Some clients can’t shrink the count. Regulated businesses, real board governance, a family firm where the veto set is a family. Don’t present the line as a penalty there, because it reads as a threat and you’ll lose the job. Present it as the reason the number is what it is, and then hold the number, because the alternative is running the eight-approver project at the three-approver price and filing the shortfall under bad luck.
When a day rate is honest and a fixed fee is a lie
Two cases, and only two.
The first is a veto set that’s genuinely unknowable. Mid-acquisition, a chief executive search running, a marketing director working out their notice. You can map the approvals today and it’ll be a different map in six weeks through nobody’s fault. A fixed fee against that prices a random variable at its median and eats the right tail, and clients in that state have a long right tail. Bill time, cap it monthly so nobody gets a surprise, and say why out loud: your approval structure is going to move during this project and neither of us can price that yet.
The second is not owning the client relationship. Subcontracting into another studio’s engagement, or working under an in-house team who own the decision themselves. You’re producing thinking; somebody else is doing the agreement work, well or badly, and you can neither see it nor influence it. Fixing a fee there prices a risk you have no lever on.
Everywhere else the fixed fee is the honest instrument, on one condition: you can name every approver, you’ve met at least half of them, and the engagement settles a single decision instead of a rolling set of them. Then the remaining variance sits in your own estimating, which is yours to carry, and carrying it is a large part of what a strategy fee is actually paying for.
The question that has to be answered before you write a number
Most quotes are wrong because they get written after the brief and before the politics. You know the deliverables in the first meeting. You find out the veto count in month two, in a message that opens “just looping in Dan.”
So ask on the first call, and ask both halves, because they get different answers:
- Who has to be happy with this for it to ship?
- Who can stop it without ever being happy with it?
The second list is shorter, harder to extract, and it’s the one that prices the job. Keep it for the end of the engagement too, when somebody asks what the strategy was worth and you need something countable to put on the table that isn’t revenue.
A client who tells you there’s only one decision-maker is describing how they’d like the company to work. Price the version you’ll actually meet.